In this series the development of a new apartment complex to replace outdated housing that was tore down.
A second crane is installed on a special foundation that was made earlier (photo 3), it serves the work on a second building (Photo 3, 4). To prevent a collusion between the two cranes it is lower and it has a horizontal beam which is shorter than the distance between them (photo 1).
1
2
3
4
5
6
In areas where the ground beams are ready prefab concrete slabs are put on top (photo 5, 6). I guess this is actually the floor of the garage below the main building. The top edge of the wall on the left side (photo 5) is ground level, it marks the height of the garage.
(c)BAP | Jun 27, 2016
Update July 11, 2016. Correction of title.